Abbot Point Bund 1 Rail Replacement

At Abbot Point TEAM Group (Aust) removed and replaced the stacker reclaimer rails on bund 1 that had

exceeded its design life due to age and corrosion

Our work covered:

  • removal of old rails

  • removal of Pandrol clips

  • transportation of  60m long sections of rail and position on bund

  • installation and welding of the rail

  • performing NDT on welds

  • alignment of the rail and survey to confirm alignment

  • grouting of  sole plates

  • moving SR to new rail section and repeat steps to replace balance of rail.